BOWER HILL SIDEWALK UPDATE:
At no cost to the township, Youngblood Paving is currently working to fix the deficient work that was done by a different contractor on the Bower Hill sidewalk.
This will be occurring between Rockhill Road and Painters Run Road.
One lane will be closed from now until Friday, September 4 during the hours of 7 AM to 5 PM.
From Tuesday, September 8 to Friday, September 11, the inside lane will be closed all day due to forming and pouring the outside curb
From Monday, September 14 to Wednesday, September 16, it will be closed all day as well due to pouring outside of the curb.
Assuming the weather does not interfere, Youngblood paving is expecting to finish on Wednesday, September 16.